Which of the following represents an attempt to balance the benefits of stability in the production plan against the benefits of responding quickly to new orders?


A) safety stock
B) safety time
C) bills of material
D) time fences
E) fixed-period lot sizing

F) All of the above
G) D) and E)

Correct Answer

verifed

verified

Refer to this product tree Refer to this product tree   If 24 Ys are needed, and on-hand inventory consists of 15Xs and 7As, how many Rs will be needed? A) 84 B) 154 C) 284 D) 310 E) 384 If 24 Ys are needed, and on-hand inventory consists of 15Xs and 7As, how many Rs will be needed?


A) 84
B) 154
C) 284
D) 310
E) 384

F) C) and E)
G) B) and C)

Correct Answer

verifed

verified

An MRP system that is updated periodically to account for all changes which have occurred within a given time interval is called a(n) ________ system.


A) pegging
B) planned order release
C) net-change
D) regenerative
E) exception report

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

The output of MRP is


A) gross requirements.
B) net requirements.
C) a schedule of planned orders for all parts and end items.
D) inventory reorder points.
E) economic order quantities and reorder points.

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

The master schedule needs to be for a period long enough to cover the stacked or cumulative lead time necessary to produce the end items.

A) True
B) False

Correct Answer

verifed

verified

An assembly-time chart indicates gross and net requirements taking into account the current available inventory.

A) True
B) False

Correct Answer

verifed

verified

Load reports show capacity requirements for departments or work centers which may be more or less than the capacity available in that work center.

A) True
B) False

Correct Answer

verifed

verified

One reason that accurate bills of material are important is that errors at one level become magnified at lower levels because of the multiplication process used by MRP.

A) True
B) False

Correct Answer

verifed

verified

The _________ of ERP makes it valuable as a strategic planning tool.


A) Internet base
B) rapid batch capability
C) employee focus
D) real-time aspect
E) database structure

F) C) and D)
G) B) and E)

Correct Answer

verifed

verified

In many organizations, information flows much more freely within functions than it does across functions. __________ represents an expanded effort to overcome this tendency.


A) MRP
B) ERP
C) CRP
D) MRP II
E) DRP

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Net requirements equal gross requirements minus safety stock.

A) True
B) False

Correct Answer

verifed

verified

MRP, considering inventory position, bills of material, open purchase orders, and lead times guarantees a feasible production plan if the inputs to MRP are accurate.

A) True
B) False

Correct Answer

verifed

verified

MRP II did not replace the basic MRP.

A) True
B) False

Correct Answer

verifed

verified

Project management approaches can help in a conversion to an ERP system.

A) True
B) False

Correct Answer

verifed

verified

One of the primary output reports of MRP concerns changes to planned orders.

A) True
B) False

Correct Answer

verifed

verified

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand   Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. When should an order for carved chocolate eggs be released? A) at the start of week 2 B) at the start of week 3 C) at the start of week 4 D) at the start of week 5 E) at the start of week 6 Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. When should an order for carved chocolate eggs be released?


A) at the start of week 2
B) at the start of week 3
C) at the start of week 4
D) at the start of week 5
E) at the start of week 6

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

In MRP, scheduled receipts are


A) identical to planned-order receipts.
B) identical to planned-order releases.
C) open orders (that is, ordered before the first time bucket, but not delivered yet) .
D) net requirements.
E) available-to-promise inventory.

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

ERP began in manufacturing organizations but has spread into service organizations.

A) True
B) False

Correct Answer

verifed

verified

Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot) , and quantities on hand   Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. What is the net requirement for dark chocolate truffles to fill this order? A) 100 B) 140 C) 150 D) 180 E) 200 Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. What is the net requirement for dark chocolate truffles to fill this order?


A) 100
B) 140
C) 150
D) 180
E) 200

F) D) and E)
G) B) and E)

Correct Answer

verifed

verified

Initially, the output from MRP may not represent a feasible schedule.

A) True
B) False

Correct Answer

verifed

verified